From the Engineering Firm, SEH Inc:
As many of you know, Centerpoint Energy has been performing utility work (gas main relocation) along St. Anthony Parkway and surrounding roadways (Main Street, California St., Columbia Ave., 31st Ave.). Centerpoint Energy anticipates that it will be done with the utility work along the roadways after the first week in September, and then it will continue relocation work in the railyard through the end of September. Estimated timelines may change, but all Centerpoint Energy utility relocation work is anticipated to be done by the end of September.
Xcel Energy utility work (power line relocation) has not yet been scheduled, but may take place this year or in the Spring of 2015.
For more information, visit the project website: www.stapbridge.com